The machine tools were held because an additional valuation check had been ordered. We acted in three stages:

  1. Days 1–2: We filed a request for expedited handling with a full set of documents.
  2. Day 3: We arranged a meeting with the head of the customs clearance department.
  3. Days 4–5: We provided additional justification for the volume discount.

The check was completed early. No penalty was charged. The production schedule was kept.